Write-off of materials and waste in production
04.06.2025 15:06How to write off used materials?
In the production software, materials can be written off in the following ways:
1. When finished products are released — written off automatically.
2. Using the “Write off all materials” action in the production act.
3. When performing operations via Route Sheets:
-
When the material is linked to the operation — automatically.
-
By the “Write-off” operation — with quantity adjustment.
1. Automatic write-off of used materials when releasing finished products
If no other method of writing off materials is set, Torgsoft automatically writes off used materials after the release of finished products, including when defective goods are written off.
Regardless of whether the item was written off due to a defect or successful release of the product was recorded — Torgsoft will write off the materials and equivalents used to manufacture the given items.
The release and write-off of products is performed in the “Production Acts” tab. Go to the “Document” menu — “Finished Product Manufacturing” — select a Production Act and click the required button “Release finished products” or “Write off item” — fill in the opened forms, specify the quantity of produced or defective goods:

2. Writing off used materials using the “Write off all materials” action in the Production Act
Materials can be written off manually. In the Production Acts the “Write off all materials” action is available . To write off all materials at once, click the “Write off all materials” button
, and the program will write off all materials from the warehouse for the given Production Act (does not apply to route sheets):

If you accidentally wrote off materials and want to cancel this action — click the “Cancel write-off of all materials” button :

3. Writing off materials during operations in Route Sheets
Route Sheets are used for employees to record the completion of each operation. In the Torgsoft software for production, you can select the type of operation when filling in the Product’s Technological Card: «Weighing», «Operation», «Write-off». To ensure the software writes off materials after each completed operation, the material must be "linked" to the operation.
-
For operations of type «Weighing» and «Operation» — materials will be written off according to the quantity specified in the Technological Card.
-
For operations of type «Write-off» — the material quantity to be written off can be adjusted manually.
How to link a material to an operation?
To link a material to an operation in the “Operation Material” table, click the “Add” button, select “Operation Material” and “Material write-off method”
-
Proportionally to the number of operations
-
All material during the first operation
-
All material during the last operation

Click “Save”.
Note: For operations of type “Weighing” or “Operation”, a material cannot be linked to multiple operations at once — only to one. A single material can only be linked to several operations simultaneously if all those operations are of type “Write-off”. However, to avoid confusion and errors in accounting, it is better to associate different materials with each operation in the production process.
How to write off materials using the “Write-off” operation?
If you set the operation type to «Write-off» — upon recording the completion of the operation in the Route Sheet, you will be able to manually specify the amount of material used.
This is convenient when you don't know exactly how much material will be used for production, and you have indicated an approximate quantity in the Technological Card, but want the software to write off materials based on the actual amount used. This scenario is common at the beginning of production, when the entrepreneur is just launching the manufacturing line, studying the process, and determining how much material is actually consumed per product unit.
Write-off acts for materials can be viewed in “Document” — “Finished Product Manufacturing” — “Production Acts” — “Write-off Acts”:

What to do with production waste and how to record it?
Most often, not all materials are fully used in the production process. For example, trimming fabric or cardboard creates scraps. To account for such waste in the software, their quantity must be specified when adding materials to the product's Technological Card.
Waste can be divided into 3 types:
-
Reusable in the same production operation, such as glue, unset polymer, glitter, etc.
-
Reusable for another stage of production, e.g., fabric, lace, or cardboard scraps unsuitable for sewing shoes but usable as filler or recyclable by another company.
-
Completely unusable waste that must be disposed of — simply thrown away.
If the waste is unusable for further production — everything is simple: you don’t need to specify any waste, and Torgsoft will write off materials based on the quantity set in the Technological Card.
If the waste is reusable — the remaining material must be returned to the warehouse. How to do this?
1. Waste reused in the same operation
The waste must be returned to the warehouse in the form of the same material it originated from.
This mostly applies to liquids and bulk materials. For example, producing one pair of shoes requires 3 ml of glitter. In reality, only 1 gram remains on a pair of sneakers, but it cannot be evenly distributed in such a small amount. Therefore, a large quantity is applied, and the excess is reused. The glitter waste is returned to the warehouse as glitter.
How to record waste as the original material?
To register such waste in the warehouse, specify the waste quantity in the “Materials” section of the Technological Card:

Check the “Return waste to warehouse” box and click “Save”:

Nothing else needs to be specified.
How does it work?
In the example, 3 grams of glitter are specified, of which 2 grams are waste. So for each pair of shoes, 3 grams will be written off, but 2 grams will be returned to the warehouse as “Glitter”, resulting in only 1 gram being deducted from stock.
You might think: why not just specify 1 gram? — This waste scheme is used when employees need to know how much material to use for one unit based on the Technological Card.
2. Waste reused in another operation or sent for recycling
Sometimes, waste cannot be reused in the same operation but can be reused in another way. In this case, it should be returned to the warehouse as a new material, not the original one.
This mostly applies to cut materials: fabric, leather, fur, cardboard, etc. For example, making shoe inserts requires 450 cm² of cardboard. Waste may be 90 cm² — not enough for another insert, but suitable as filler or recyclable. Such waste is returned as a new material.
How to record waste as a new material?
For example, you want to return waste from “Cardboard” as “Filler”. Do the following.
In the Technological Card, specify “Waste quantity” for the material and check the “Return waste to warehouse” box:

On the right, you’ll be able to select a material from the directory. Add “Filler” to the directory, select it, and enter it in the “Waste material” field. Click “Save”:

Now, after each operation, the program will write off 450 cm² of “Cardboard” and receive 90 cm² of “Filler”.
Materials with returned waste can be viewed in the “Waste Receipt Acts” tab.
-
18.12.2025
Technological map, Production act and Route sheet: a system of production documents
Production automation in Torgsoft: technological map, production act and route sheet, control of operations, materials and cost
-
08.12.2025
How to organize accounting for raw materials and semi-finished products in Torgsoft
Automated accounting of materials and raw materials in Torgsoft: posting, reservation, write-off, balance control and production planning
-
03.12.2025
How to organize production: technological maps, planning and availability of resources
Automation of production in Torgsoft: technological maps, planning, layout of materials, reservation and management of resources for accurate start of the cycle









Go back to the previous step